Here you can follow the construction progress from 2021 of the VIDO Project.
Construction phase 1: Production of construction pit 70%, placement of basement walls and laying of floor slab reinforcement; production of ceiling above KG in partial areas; Construction phase 2: Scaffolding of the facades, completion of work stone work, continuation of tile work, continuation of technical expansion of apartments and heating center, clearing of underground garage ceiling for production of waterproofing.
Construction phase 1: Production of excavation pit 45 % and start of basement walls in the area of the produced floor slab; Construction phase 2: In partial areas, completion of facade and placement of substrate on the roofs, completion of drywall construction, tiling work, installation of balustrades, continuation of technical equipment, start of ashlar work on staircases.
Construction phase 1: Production of construction pit 35 % and start of production of clean layer and reinforcement of floor slab; Construction phase 2: Production of facade and roofs, completion of rough installation of technical equipment, continuation of screed work.
Shell construction in the 2nd construction phase is completed -> Interior work has started – Shell construction work in the 1st construction phase has started.
Current construction status: Earthworks for the 1st construction phase are currently in progress. Expected start of shell construction work planned for the beginning of July 2021. Completion of shell construction work in the 2nd construction phase planned by the end of May 2021. After that, start of interior construction work.
Current construction status: 1st construction phase – earth excavation begins, 2nd construction phase – almost completion of shell.
Current construction status: Ceiling above basement finished. House 12: Walls + ceiling 1st floor finished.
Completion of the concreting work of the floor slab and reinforcement work of the ceiling above the basement.