NEWS FROM THE CONSTRUCTION SITE

Here you can follow the construction progress of the VIDO Project.

AUGUST-OCTOBER 2020

The building pit of the underground car park has been excavated. The construction crane is erected.

1 / 4

2 / 4

3 / 4

4 / 4

JULY 2020

Most of the shoring work has been completed. Advance excavation for placing the back anchoring is carried out. 

1 / 4

2 / 4

3 / 4

4 / 4

APRIL 2020

Construction roads and working levels for the large equipment are laid out. 

1 / 3

2 / 3

3 / 3

FEBRUARY 2020

Preparatory measures of the site. 

1 / 4

2 / 4

3 / 4

4 / 4