NEWS FROM THE CONSTRUCTION SITE
Here you can follow the construction progress of the VIDO Project.
JANUARY 2021
Completion of the concreting work of the floor slab and reinforcement work of the ceiling above the basement.
DECEMBER 2020
The floor slab is currently being concreted and the first walls in the basement are being erected.
OCTOBER 2020
The 1st crane for the building construction has been erected and the work on the base plate of the 2nd construction phase has begun.
AUGUST & SEPTEMBER 2020
The building pit of the underground car park has been excavated. The construction crane is erected.
JULY 2020
Most of the shoring work has been completed. Advance excavation for placing the back anchoring is carried out.
APRIL 2020
Construction roads and working levels for the large equipment are laid out.
FEBRUARY 2020
Preparatory measures of the site.